Project Schedule, Project Cost Analysis and Forecasting
Project Schedule, Project Cost Analysis and Forecasting |
Schedule Analysis and Forecasting
| |||
EVM Parameter
|
Project Management Questions addressed
|
How to Calculate?
|
What it implies?
|
Schedule Variance (SV)
|
Are we ahead or behind schedule?
|
SV = EV-PV
SV% = SV/PV
|
A Positive SV indicates projects is ahead of schedule
A negative SV indicates project is behind schedule
If SV is negative then X% indicates that the project is x% behind schedule.
|
Schedule Performance Index (SPI)
|
How efficiently are we using time?
|
SPI = EV/PV
|
SPI < 1 indicates behind schedule
SPI = 1 indicates on schedule
SPI > 1 indicates ahead of schedule
|
Time Estimate At Completion (EACt)
|
When are we likely to finish work?
|
EACt = (Original estimated project completion time) / SPI
|
Indicates estimated project completion time based on current trends
|
Cost Analysis and Forecasting
| |||
EVM Parameter
|
Project Management Question addressed
|
How to Calculate?
|
What it implies?
|
Cost Variance (CV)
|
Are we under or over budget?
|
CV = EV-AC
CV% = CV/EV
|
A Positive CV indicates cost under run
A negative CV indicates cost overrun
If CV is negative then X% indicates that the project is x% over budget for the work performed till to date
|
Cost Performance Index (CPI)
|
How efficiently are we using our resources?
|
CPI = EV / AC
|
It implies Rs X worth of work performed for every Re spent
If CPI is greater than 1, under budget
If CPI is less than 1, cost over run.
|
To Complete Performance Index (TCPI)
|
How efficiently must we use our remaining resource
|
TCPI =
(BAC – EV ) / (BAC-AC)
|
This implies that to achieve the BAC the performance have to improve from current CPI to the calculated TCPI for the remaining work
|
Estimate At Completion (EAC)
|
What is the project likely to cost?
|
EAC = BAC / CPI
EAC = AC + ETC
EAC = (AC/EV) / BAC
EAC = AC/EV (Work completed & in progress) + (Work not yet begun)
EAC =
AC+[1/CPI(BAC-EV)]
|
Indicates the final cost of the project if the current performance trends continue
|
Variance At Completion (VAC)
|
Will we be under or over budget?
|
VAC = BAC – EAC
VAC% = VAC / BAC
|
If the current trends continue then the project will cost an additional x unit of resources than originally planned
|
Estimate to Complete (ETC)
|
What will the remaining work cost?
|
ETC =
( BAC – EV ) / CPI
|
Based on efficiency to date measured by CPI an estimate to complete can be worked out
|
Post a Comment