Check List to Take Over An Existing Project
Check List to Take Over An Existing Project |
Contract Management:
- A clear and well defined tender specifications duly signed by buyer and seller clearly mentioning detailed scope of work.
- Letter of Acceptance of the Project Order enlisting deviations in the contract if any.
- List of project deliverable at various stages of the project like engineering, procurement and construction.
- Project Kick off Meeting Minutes between the project team members.
- Project Kick off Meeting Minutes between the project team and the buyer.
- Total no of project change order requests approved by the buyer indicating changes in costs, and project schedule.
- Detailed Project Costing sheet.
- Minutes of meeting of all meetings held between buyer and the PM / Project Team.
- Copies of all project status reports submitted to the buyer.
- List of major bottlenecks in the project and suggested remedial action.
- Accepted baseline project schedule indicating critical milestones.
- Project Communication matrix.
- List of key project stake holders indicating their influence over the project.
- Scope matrix clearly highlighting buyers scope during different phases of the project.
- Project organisation Chart with roles and responsibility of each project team member.
- Project Management Plan if available.
- Present status of the project cash flow
- Client accepted billing schedule
- Details of the total actual costs booked on the project
- Deviation in planned vs. actual cost booked on the project.
- Cash flow forecasts.
- Project close out criteria as mentioned in the tender / contract documents
- Buyer’s responsibility during the performance trials and handing over of the plant.
- Copies of all communication sent to the customer.
Engineering Documents:
- Client approved drawing and document schedule
- Check if the approved drawing and document schedule have been incorporated in the project schedule.
- Updated document control index.
- List of engineering drawings and documents approved by the customer.
- List of engineering drawings and documents pending for client approval.
- List of engineering drawings and documents pending for submission and their revised submission deadlines
- Check if the approved document confirms to the tender specifications. List deviations if any.
- List of drawings issued "for construction" to various vendors.
- Project Quality assurance plan
- Quality assurance plan of each equipment.
- Method Statements
- Bill of quantities for various sections of the project or overall project.
- Design calculations.
Procurement Management:
- Client approved vendor list for all streams of engineering like mechanical, electrical, process, instrumentation, automation.
- List of purchase orders issued and their delivery schedule.
- List of items pending for client inspection.
- Manufacturing status of all equipment with various vendors.
- Inspection schedule at various manufacturing facilities.
- List of long lead items
- List of items pending for purchase
- Are all vendors having the latest version of the approved drawings
- Are all vendors working as per the approved QAP’s
- Have all Vendors understood their scope of supply.
- Any vendor who is unable to meet the delivery schedule and reason for the same.
- Vendor’s who have demanded extra cost/delivery time and reasons for the same.
Construction Management:
- Client approved Construction Plan
- Construction organisation
- Client approved Method Statements
- Site Mobilizations Plan
- Work orders issued till date
- Work orders pending for issuance
- Construction SOP’s as enlisted in the contract
- Client’s Daily Work Permit Procedure.
- Safety Procedures to be adopted
- Material storage facility at site
- Can the stored material be identified and traced to approved engineering documents
- Record of material issue
- Record of material damaged at site and replacement plan.
- Client imposed erection and commission milestones if any.
- List of activities that have missed the milestone
- Frequency of progress reporting and progress reporting formats if any.
- Daily Progress Reports
- Cost status of construction activities.
- Deviation in construction cost with respect to the planned.